Technical Route
The structure was built as a stable elevated working platform, with sufficient load capacity and workspace for controlled transfer of heavy steel plates.
Each transport involved approximately 2,500 kilograms moved to the upper floor. The platform was engineered for a total load of approximately 3,000 kilograms, including four workers present at the same time. Stability, safe walking routes, and clear work coordination were the foundation throughout execution.